Skyward Drive, Sudbury

Construction Notice

Construction Startup Notice- May 12, 2025

Pavement Rehabilitation and Resurfacing- Skyward Drive, Sudbury  

The City of Greater Sudbury will be completing road improvements on Skyward Drive between Arnold Street and Telstar Avenue, in Sudbury.

Construction by the City’s contractor, Green Infrastructure Partners will begin June 2025 and is expected to be completed October 2025.

Work will typically take place during daylight hours Monday to Friday. Weekend or night work may be required.

Note: Skyward Drive is included in a multi-location contract. As a result, the timing of the work outlined in this notice may be subject to change.

Construction Details:

  • Replacement of concrete curbs
  • Remove and replace surface asphalt
  • Drainage Improvements

Project Manager:
Andrew Peltomaki
705-690-5541


Project Timeline:

  • May 12, 2025 - Construction Startup Notice
  • March 24, 2025 - Pre-Construction Notice