Ethelbert, Ernest and Maple Streets, Sudbury

Project Update

Season Wrap Up Notice - November 17, 2026

Road Reconstruction 

Construction by the City’s contractor, GIP Interpaving, will be wrapping up for the 2026 season in the coming weeks. 

Work will resume in the spring with completion expected in fall 2027. 

A Construction Notice will be provided to residents before work resumes next year.

File:  ENG25-4

Project Manager:
Andrew Peltomaki

For inquiries outside regular business hours, please contact 311. 


Remaining Construction Work:

Ethelbert Street (Maple to Linden Streets): 

  • Watermain and sanitary sewer upgrades
  • Concrete curb and sidewalk work
  • Asphalt placement

Maple Street: 

  • Watermain and sanitary sewer upgrades in the cul-de-sac
  • Curb and asphalt replacement in the cul-de-sac

All Locations: 

  • Spot concrete sidewalk and curb repairs
  • Surface asphalt placement and line painting
  • Miscellaneous restoration such as sod, retaining walls, driveway tie ins, etc.

Project Timeline:

  • Season Wrap Up Notice - November 17, 2026
  • Construction Notice Update - June 22, 2026
  • Season Start-up - April 17, 2026
  • Construction Start-up - July 8, 2025
  • Pre-Construction Public Information Meeting Notice - April 15, 2025
  • Pre-Engineering Work Notice - October 21, 2024