Construction Startup Notice- August 15, 2025

Road Reconstruction

The City of Greater Sudbury will be completing road and water/wastewater improvements on Maple Street between the dead end and Parkwood Street, and Parkwood Street between Maple Street and the dead end, in Sudbury.

Construction by the City’s contractor, Dominion Construction will begin August 2025, and is expected to be completed November 2025. 

Work will typically take place during daylight hours Monday to Friday. Weekend or night work may be required.

Final asphalt will be completed in 2025. 

Construction Details:

  • Watermain replacement
  • Storm sewer repairs
  • Sanitary sewer replacement on Maple Street
  • New curb and sidewalk
  • New road asphalt
  • Rock removal

Project Manager:
Jody Rybachuk
705-674-4455 extension 4493


Project Timeline:

  • Public Information Meeting- May 15, 2025
  • Pre-Engineering Work Notice- October 21, 2024