Struthers Street, Sudbury

Road Reconstruction, Intersection Realignment, Water and Sewer Replacement

The City of Greater Sudbury will complete road and water/wastewater improvements on Struthers Street, between Junction Creek and Regent Street, in Sudbury.

Construction by the City’s contractor, Teranorth Construction & Engineering Limited will begin April, 2023, and is expected to be completed November, 2023. 

Work will typically take place during daylight hours.

Weekend or night work may be required.

Final asphalt will be completed in 2024.

Construction Details: 

  • Realignment of the 5-way intersection
  • Roadway reconstruction 
  • Replacement of concrete curb, sidewalk and asphalt
  • Replacement of watermain, including services
  • Replacement of sanitary sewer main, including services
  • New storm sewer system within roadway

Construction Notice
Pre-Construction Notice

How Will you Be Impacted By Construction
Temporary Water Bypass System
Will There Be Any Impact of Services
What to Expect During Construction

Project Manager
Krista Trafford