Larch Street, Sudbury

Season Wrap Up

Road Reconstruction

The City of Greater Sudbury has completed the road and water/wastewater improvements on Larch Street between Elgin Street and Lisgar Street, in Sudbury for the 2023 construction season.

Construction by the City’s Contractor, Teranorth Construction & Engineering Ltd. will resume spring, 2024 and is expected to be completed summer, 2024.

A Construction Notice will be issued prior to the commencement of the 2024 construction season.

Remaining Construction Work: 

  • Surface Asphalt Placement
  • Permanent Line Painting 
  • Stamped Asphalt Cross Walks
  • Installation of Tactile Warning Surfaces at intersections
  • Miscellaneous Repairs

Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.

Season Wrap Up 2023 Notice

Construction Notice - Road Closure

Construction Notice - 2023 Start Up Notice

Construction Notice - May 2022

Existing Design vs Proposed Design

Pre-Construction Notice - Feb 2023

Questions about upcoming construction can be directed to:
Project Manager:
Miranda Edwards
705-923-1350
Miranda.Edwards@greatersudbury.ca