Elgin Street, Sudbury
Project Update
Construction Startup Notice - January 19, 2026
Pavement Rehabilitation & Infrastructure Improvements, Elgin Street, Sudbury
The City of Greater Sudbury will be completing road and water/wastewater improvements on Elgin Street, between Elm and Brady Streets, in Sudbury.
Construction by the City’s contractor, Teranorth Construction & Engineering Ltd. will begin April 2026 and is expected to be phased over two construction seasons with completion expected July 2027.
Final asphalt will be completed in 2027.

Construction Details:
- New asphalt and concrete curbs
- Pedestrian walkways on both sides of the road
- Cycle tracks
- Intersection improvements at Durham and Elgin Streets
- Watermain rehabilitation
- Storm sewer replacement
- Street lighting improvements
Project Manager:
Andrew Peltomaki
705-690-5541
Project Timeline:
- January 19, 2026 - Construction Startup Notice
- October 24, 2025 - Project Overview Notice
- December 18, 2024 - Pre-Construction Notice