Anderson Drive, Lively

Project Update

Construction Notice Update- August 5, 2025

Road, Water and Wastewater Improvements

Dear Resident,

The City of Greater Sudbury is providing an update on construction work for Anderson Drive, between Meagan Duhamel Drive and Third Avenue.

The City paused this work for the 2024 construction season to allow Hydro One time to plan and complete underground work. During earlier construction between Woodland Avenue and MR24, crews identified that the underground hydro system needed upgrades to meet current standards.

Hydro One work has been completed and the City’s contractor, Belanger Construction will begin work on Anderson Drive.

The 2025 construction season will include restoration work from Meagan Duhamel Drive to Woodland Avenue as well as the continuation of watermain work along Anderson Drive from Woodland Avenue to approximately 50m west of Woodland Avenue.

The remainder of the work along Anderson Drive from Woodland to Third Avenues will take place during the 2026 construction season.

The City of Greater Sudbury operates a 24-hour answering service for urgent municipal matters. You can call 311 any time or email 311@greatersudbury.ca. Staff check emails during regular business hours.
 

Project Manager:
Andrew Peltomaki
705-690-5541


Project Highlights:

  • Replace and install new watermain;
  • Replace and install new sanitary sewer main;
  • Replace and install new storm sewer main;
  • Roadway reconstruction.

Project Timeline:

  • Construction Notice Update- August 5, 2025
  • Construction Notice Update- April 30, 2025
  • Construction Notice Update- July 4, 2024
  • Construction Notice- June 16, 2023
  • Pre-Construction Notice- March 16, 2023

Construction FAQs