Anderson Drive, Lively
Project Update
Season Start-up Notice - April 1, 2026
Lively/Walden Infrastructure Improvements, Phase 2C & 2D, Lively
The City of Greater Sudbury will be continuing road and water/wastewater improvements on Anderson Drive, between M.R. 24 and Third Avenue, in Lively.
Construction by the City’s contractor, Bélanger Construction, will begin May 2026 and is expected to be completed in the fall of 2026.
Work will typically take place during daylight hours Monday to Friday. Weekend or night work may be required.
Final asphalt will be completed in 2027.
*Timelines are subject to change*

Project Manager:
Andrew Peltomaki
705-690-5541
Construction Details:
- Road reconstruction and active transportation improvements
- Watermain Replacement
- Sanitary Sewer Replacement
- Storm Sewer Replacement
- Streetlighting improvements
- Driveway and property restoration
Project Timeline:
- Season Start-up Notice-April 1, 2026
- Construction Notice Update- August 5, 2025
- Construction Notice Update- April 30, 2025
- Construction Notice Update- July 4, 2024
- Construction Notice- June 16, 2023
- Pre-Construction Notice- March 16, 2023