Demolition Begins on Ledo Hotel as Part of Downtown Redevelopment Process
Jan 2, 2024
The demolition of the former Ledo Hotel at 300 Elgin Street is set to begin on Monday, January 8 and is expected to take four weeks to complete.
The property is one of a number that was acquired by the City to advance redevelopment in the downtown south district. The historic investment is an important step as City Council considers a new build or a refurbished arena in the downtown.
Preparations to ready the site are currently underway.
During the demolition lane and sidewalk closures will ensure motorist and pedestrian safety. They are as follows:
- The eastbound lane of Van Horne Street will be closed from Minto Street to Shaughnessy Street.
- The westbound lane on Elgin Street will be closed from Van Horne Street to Shaughnessy Street, including the adjacent sidewalk.
- Romanet Lane will be closed in both directions from Van Horne Street to Elgin Street
In an effort to divert waste from the landfill, materials will be segregated during the demolition process and placed in separate bins to maximize recycling.
The demolition of surrounding buildings in the same block will follow soon after the completion of the Ledo demolition.
Checks of the vacant buildings are being carried out regularly to ensure they are not being occupied.
More information about downtown redevelopment is available online.