The 2024 construction season is underway and there are several major projects with Council-approved budgets that will begin this year, including:

  • Nelson Street pedestrian bridge replacement - $3 million
  • Lasalle Boulevard reconstruction and upgrades from Falconbridge Road to Elisabella Street as part of the Employment Land Strategy Implementation – $19.4 million
  • St. Charles Lift Station reconstruction and expansion - $19.7 million
  • Capreol trunk storm sewer upgrades and road reconstruction from Crescent to Ormsby Avenues - $7.2 million
  • Junction Creek reprofiling and rehabilitation from Lloyd Street to CN tracks - $10 million
  • Highway 17 trunk watermain replacement - $2.4 million 

For an interactive map of current, ongoing construction projects please visit greatersudbury.ca/constructionprojects

In 2023, there was a total investment of more than $74 million into the city’s roads, water, sewer and active transportation networks, as well as bridges and large culverts at a total of 168 locations across Greater Sudbury.

By the Numbers: 2023 roads, water, sewer and active transportation networks

  • Installed 6,650 metres of active transportation infrastructure, including sidewalk and trails at 13 locations
  • Completed 27,050 square metres of large asphalt patches at 18 locations
  • Installed 9,830 metres of concrete curb and gutter at 15 locations
  • Installed 2,490 metres of new guide rail at 14 locations
  • Installed 72 new streetlights
  • Rehabilitated 5 bridges
  • Performed 1,150 metres of watermain lining at six locations
  • Replaced 1,320 metres of watermain at four locations
  • Installed 15,700 new Advanced Metering Infrastructure (AMI) meters
  • Completed nearly 4,000 metres of sanitary lining at 20 locations
  • Replaced 5,360 metres of sanitary sewer at four locations
  • Tendered four new water/wastewater facility projects
  • Replaced 2,020 metres of storm sewer at 12 locations
  • Installed 850 metres of culverts at 22 locations
  • Rehabilitated nine sports courts