David, Marion and Paris Streets including Ramsey Road, Sudbury

Season Wrap Up

Construction Notice- December 4, 2025

Road Reconstruction, David and Marion Streets, with Storm Sewer Upgrades to Ramsey Lake (Bell Park), Sudbury

 

The City of Greater Sudbury has completed road and water/wastewater upgrades on David Street, from 30 metres east of Paris Street to its west end, and on Marion Street, from its north end to McNaughton Street.

This project also includes road improvements and storm sewer upgrades on Ramsey Road and Paris, McNaughton, Facer Streets.

Construction by the City’s contractor, Teranorth Construction & Engineering Ltd., will resume in spring and is expected to be completed summer 2026. 

A Construction Notice will be issued before the beginning of the construction season next year.

Project Manager:
Krista Trafford
249-377-9760


Remaining Construction Work:

  • Replacement of storm sewer on Facer Street at Paris Street.
  • Placement of new asphalt at the intersection of Facer and Paris Streets.
  • Any outstanding property and driveway restoration

Project Timeline:

  • Season Wrap Up Notice - December 4, 2025
  • Construction Notice- April 22, 2025
  • Resident Letter - December 2024
  • Construction Notice- April 3, 2024
  • Public Information Meeting (David Street and Marion Street, Sudbury)- February 28, 2024
  • Public Information Meeting (Paris Street, McNaughton Street and Ramsey Road, Sudbury)- February 28, 2024
  • Construction Update letter 2023- July 26, 2023
  • Public Consultation Meeting- May 5, 2023