Goodview Road, Sudbury

Project Update

Construction Notice- July 23, 2024

Pavement Rehabilitation & Resurfacing

The City of Greater Sudbury will be completing road improvements on Goodview Road between M.T.C and C.K.S.O Roads in Sudbury.

Construction by the City’s Contractor, GIP Interpaving Limited will begin August, 2024 and is expected to be completed by October 2024.

Work will typically take place during daylight hours Monday to Friday. Weekend or night work may be required. 

Project Manager:
Andrew Peltomaki
705-690-5541


Project Highlights:

  • Remove and replace asphalt 
  • Drainage improvements 
  • Replacement of existing road cross culverts

Project Timeline:

  • Construction Notice- July 23, 2024
  • Pre-Construction Notice- May 28, 2024