The City of Greater Sudbury has completed wastewater infrastructure improvements in various locations.

Construction by the City’s Contractor, Insiuform Technologies Limited, began in July 2023 and was completed in November 2023.

Work will typically take place during daylight hours Monday to Friday.

Locations include:

  • Bond Street - between the west end of the street (dead end) and Notre Dame Avenue
  • Brodie Avenue - between Victoria and Elm Streets
  • Buchanan Street - between Sandra Boulevard and Haig Street
  • Bulmer Avenue - between Lorne and Mary Streets
  • Clinton Avenue - between Bond and Perreault Streets
  • Dean Avenue - between Jane and Landsend Streets
  • Douglas Street - between Regent and Lorne Streets
  • Edna Street - between Lorne and Haig Streets
  • Logan Avenue - between Lorne and Landsend Streets
  • Melvin Avenue - between Mabel Avenue and Dell Street
  • Morrison Avenue - between Lorne and Mary Streets
  • Mountain Street - between Mont Adam and Harvey Streets
  • Murray Street - between Leslie and Bond Streets
  • Nolin Street - between the west end of the street (dead end) and Notre Dame Avenue
  • Perreault Street - between Notre Dame and Percy Avenues
  • Reginald Street - between Ash Street and the north end of the street (dead end)
  • Roxborough Drive - between the west end of the street (dead end) and Laura Avenue
  • Tuddenham Avenue - between Irving Street and Logan Avenue
  • Victoria Street - between Rudd and Albinson Streets
  • Whittaker Street - between Isabel and Victoria Streets

Project Manager:
Jody Rybachuk
705-674-4455, extension 4493


Project Highlights:

  • Structural sewer lining of the existing sewer
  • No road excavation required