The building code only requires a 15m setback from the water, but the amendment proposes a setback of 30m. Which setback prevails?

Tthe Zoning By-law is applicable law under the Building Code and Public Health Sudbury & Districts will be required to issue septic system permits that comply with the Zoning By-law setback of 30m.