Edna Street, Chelmsford

Project Update 

Construction Startup Notice- October 22, 2026

Sanitary Sewer Replacement

The City of Greater Sudbury will be completing road and wastewater improvements on Edna Street between St. Albert Street and Windstar Avenue, in Chelmsford.

Construction by the City’s contractor, Bélanger Construction, will begin in late October and is expected to be completed in November 2026.

Work will typically take place during daylight hours Monday to Friday.

Final asphalt will be completed with the surface asphalt during the subdivision phase. 
 

Project Manager:

Kevin Reynish

For inquiries outside regular business hours, please contact 311. 


Construction Details:

  • Removal of existing pavement
  • Sanitary sewer replacement
  • Cured in place lining of sanitary sewer
  • Placement of new pavement

Project Timeline:

  • Construction Startup Notice- Oct 22, 2026
  • Construction Startup Notice- June 10, 2026

Construction FAQs