2025
Crescent and Ormsby Avenues, Capreol
Project Update
Season Start-Up - May 13, 2025
Capreol Trunk Storm Sewer Upgrades
The City of Greater Sudbury will be continuing road improvements on Crescent Avenue from Young Street to Ormsby Avenue, Ormsby Avenue from Crescent Avenue to Dennie Street, and Dennie Street from Ormsby Avenue to Crescent Avenue.
The final phase of construction by the City’s contractor, Teranorth Construction, will begin spring, 2025 and consists of project clean up and restoration. The work is expected to be completed by summer, 2025.
Work will typically take place during daylight hours Monday to Friday. Weekend or night work may be required.

Project Manager:
Kevin Reynish
705-674-4455, extension 3613
Project Highlights:
- Surface asphalt along Crescent Avenue, Ormsby Avenue and Dennie Street
- Sod work
- Driveway restoration
- Roadway restoration.
Project Timeline:
- May 13, 2025 - Construction Notice
- August 21, 2023 - Construction Notice
- May 16, 2023 - Public Information Meeting Notice
- June 1, 2023 - Public Presentation
Dominion Drive, Hanmer
Project Update
Season Start-up Notice- May 23, 2025
Pavement Rehabilitation
The City of Greater Sudbury will be continuing road improvements on Dominion Drive, from Notre Dame Avenue to 1.7 kilometres West, in Hanmer.
Construction by the City’s contractor, GIP Interpaving Limited will begin June 2025 and is expected to be completed September 2025.
Work will typically take place during daylight hours Monday to Friday. Weekend or night work may be required.

Project Manager:
Kevin Reynish
705-919-2089
Construction Details:
- Pavement rehabilitation
- Installation of paved shoulders
- Road culvert replacements
Project Timeline:
- Season Start-up Notice - May 23, 2025
- Construction Update Notice - October 3, 2024
- Construction Notice - June 14, 2024
- Pre-Construction Notice - April 11, 2024
Dupont Street, Chelmsford
Project Update
Construction Startup Notice- May 12, 2025
Culvert Replacement
The City of Greater Sudbury will be completing a road culvert replacement on Dupont Street, in Chelmsford.
Construction by the City’s contractor, GIP Interpaving Limited will begin May 2025 and is expected to be completed late summer, 2025.
Work will typically take place during daylight hours Monday to Friday.
Final asphalt will be completed in late summer 2025.

Construction Details:
- Box culvert replacement between 3670 and 3704 Dupont Street
- Guiderail installation
- Roadway restoration
Project Manager:
Kevin Reynish
705-919-2089
Project Timeline:
- May 12, 2025 - Construction Startup Notice
Larch Street, Sudbury
Project Update
Season Wrap Up- December 8, 2023
Road, Water and Sewer Improvements
The City of Greater Sudbury will continue the road and water/wastewater improvements on Larch Street between Elgin and Lisgar Streets, in Sudbury.
Construction by the City’s contractor, Teranorth Construction & Engineering Ltd. will start in spring 2023 and is expected to be completed in fall 2023.
Work will typically take place during daylight hours, weekend and/or night work may be required.
Final asphalt will be completed in Spring 2024.

Project Manager:
Andrew Peltomaki
705-690-5541
Current Construction Details:
- Surface Asphalt Placement
- Permanent Line Painting
- Stamped Asphalt Cross Walks
- Installation of Tactile Warning Surfaces at intersections
- Miscellaneous Repairs
Project Highlights:
- Watermain Replacement
- Sanitary Sewer Replacement and/or Rehabilitation
- Storm and Drainage Improvements
- Active Transportation Improvements (2 through lanes reduced to 1 through lane and the introduction of an on street cycle lane)
- Full Depth Asphalt Removal
- Supply and Placement of Asphalt
- Concrete Curb Removal and Replacement (barrier curb to be replaced with a mountable curb to improve accessibility)
- Driveway/Entrance Restoration
- Above grade planters to be replaced with at grade trees.
Project Timeline:
- Season Wrap Up- December 8, 2023
- Season Start-up Notice- April 6, 2023
- Road Closure Notice- July 18, 2023
- Construction Notice- June 1, 2022
- Pre-Construction Notice- February 23, 2022
Martin Road, Val Caron
Project Update
Construction Startup Notice - May 2, 2025
Martin Road Bridge Replacement
Martin Road, Val Caron
Work will resume this spring on Martin Road Bridge, between Valleyview Road and MR 15, in Val Caron.
Construction by the City’s contractor, Dominion Construction, will resume May 2025 and is expected to be completed June 2025.
Work will typically take place during daylight hours Monday to Friday. Weekend or night work may be required.

Project Manager:
Jody Rybachuk
705-674-4455, extension 4493
Construction Details:
Previous Seasons Accomplishments:
- Completed removal and replacement of existing bridge with a single span concrete slab on steel girder bridge with concrete foundations.
- Partial installation of approach roadside safety features including steel beam guide rails.
Remaining Activities Include:
- Final approach grading and roadside safety features including steel beam guide rails and energy attenuators.
- Binder asphalt along approaches.
- Final surface asphalt along the approaches and bridge deck.
- Final site restoration.
During the remaining construction, Martin Road Bridge will be closed to all traffic. Access to Martin Road on both sides of the bridge is available via Valleyview Rd, Belisle Dr, and MR 15.
Old Highway 69N (MR 80), Val Caron
Project Update
Construction Notice - May 7, 2024
Active Transportation Improvements
The City of Greater Sudbury will be completing active transportation improvements on Old Highway 69N (MR80), between Main Street and the mall entrance in Val Caron.
Construction by the City’s contractor, GIP Interpaving Ltd. will begin May and is expected to be completed in September 2024.
Work will typically take place during daylight hours Monday to Friday.

Project Manager:
Miranda Edwards
705-923-1350
Current Construction Details:
- Three metre wide multi-use path on the west side of Old Highway 69N (MR80) from Main Street to the Val Est Shopping Centre.
Project Highlights:
- Phase One includes the construction of a three (3) metre wide multi-use path on the west side of Highway 69N (MR80) from Main Street to the Val Caron Mall and is expected to be completed in 2023 with subsequent phases completed in future years.
Project Timeline:
- Construction Notice - September 6, 2023
- Pre-Construction Notice - June 27, 2023
Pearson Drive, Sudbury
Project Update
Construction Notice- July 23, 2024
Pavement Rehabilitation
The City of Greater Sudbury will be completing road improvements on Pearson Drive between Sunnyside Road to the end in Sudbury.
Construction by the City’s Contractor, GIP Interpaving Limited will begin August 2024 and is expected to be completed October 2024.
Work will typically take place during daylight hours Monday to Friday. Weekend or night work may be required.
Final asphalt will be completed in spring 2025.

Project Manager:
Andrew Peltomaki
705-690-5541
Current Construction Details:
- Remove and replace asphalt
- Drainage Improvements
Project Highlights:
- Pavement Rehabilitation
- Binder Asphalt Placed in 2024
- Surface Asphalt Placed in 2025
- Drainage Improvements
Project Timeline:
- Construction Notice- July 23, 2024
- Pre-Construction Notice- May 9, 2024
Surface Treatment- Various Locations, Greater Sudbury
Surface Treatment
Construction Startup Notice- May 16, 2025
The City of Greater Sudbury will be completing road improvements on various roadways listed below.
Construction by the City’s contractor, Pioneer Construction Inc. will begin May and is expected to be completed September, 2025. Each location is to be completed within four weeks from the time the construction begins.
Work will typically take place during daylight hours Monday to Friday.
Work will take place on sections of the following roads:
Single Surface Treatment:
- North Shore Black Lake Road (Lively)
- Bruno Street (Azilda)
- Bodson Drive West (Val Caron)
- Pine Hill Road (Sudbury)
Double Surface Treatment:
- Trudyville Road (Wahnapitae)
- Dryden Road East (Wahnapitae)
- Mikkola Road (Lively)
- Moxam Landing Road (Lively)
- Bonin Street (Azilda)
- Desmarais Road (Val Therese)
- Kenneth Road (Val Therese)
- Horseshoe Lake Road (Sudbury)
- Deschene Road (Hanmer)
Project Manager:
Krista Trafford
249-377-9760
Project Highlights:
Single Surface Treatment:
- Addition of Class 4 aggregate similar to sand
- Application of surface treatment also known as chip and tar
Double Surface Treatment:
- Regrading of the roadway
- Addition of granular A
- Application of surface treatment also known as chip and tar
- Match driveways to new road elevation
Skead Road - Pavement Rehabilitation
Project Update
Construction Startup Notice- May 29, 2025
Pavement Rehabilitation
The City of Greater Sudbury will be completing road improvements on Skead Road, from Airport Terminal Drive to 1.9 kilometres east, in Skead.
Construction by the City’s contractor, Pioneer Construction Inc. will begin in June 2025 and is expected to be completed September 2025.
Work will typically take place during daylight hours Monday to Friday. Weekend or night work may be required.

Construction Details:
- New asphalt including paved shoulders
- New guide rail
- Ditching
Project Manager:
Miranda Edwards
705-923-1350
Project Timeline:
- Construction Startup Notice- May 29, 2025