Map and timelines

COVID-19 Update

Project staff will not be entering homes to replace water meters while the provincial lockdown is in effect.

The City and contractor will review the situation in early February and make appropriate changes to the program as provincial restrictions are lifted or extended. A revised project schedule will be provided once a new start-up date is determined.

Appointments can still be booked for after February 15. If provincial restrictions are extended beyond that date, the contractor will contact customers to rebook.


The installation of new water meters across the city is set to be done in several stages and on a ward-by-ward basis. We expect this two-year project to be completed by the end of 2022.Please review the map below to see if we’re in your area.