Notre Dame East at Landry Street
Pre-Construction Notice
Notre Dame East at Landry Street, Azilda, Culvert Replacement
The City of Greater Sudbury Culvert Replacement on Notre Dame East at
Landry Street, Azilda, was planned for construction in August 2021.
The project has been delayed due to scheduling
conflicts with moving above/underground utilities and environmental
restrictions for timing
of in-water work.
Construction Details:
- Moving Hydro One pole and Enbridge gas main
- Culvert replacement and watermain improvements
- Bus stop relocation to west side of Landry Street
- Storm sewer improvements and roadway restoration.
Expected Start Date: Summer 2022
Expected End Date: Fall 2022
The Contractor Denis Gratton Construction Ltd.
will install signage in advance of construction
*Timeline is subject to change*
Project Manager:
Kevin Reynish
705-674-4455, extension 3613
Kevin.Reynish@greatersudbury.ca