Manninen Road - Complete

The City of Greater Sudbury will be rehabilitating Manninen Rd Bridge span over a tributary of Spanish River, approximately 350m south of Spanish River Road.

Construction Details:

• Replace existing timber decking and bridge barriers.
• Recoating steel girders.
• Detours will be provided to maintain local access, while Manninen Rd is closed.
• Installing new approach guardrail and end treatment system.
• Improved drainage by installing road drainage channels.
• Installing scour protection.
• Regrading bridge approaches.

Expected Start Date: Early Summer 2021

Expected End Date: End of Summer 2021

*Timeline is subject to change*

Public Information Notice

Transport Canada Public Notice

CGS Project Manager:
Chris Cornell, P.Eng.