Hyland Drive and Wellington Heights

Season Start-up

Road Reconstruction, Watermain and Sewer Improvements

The City of Greater Sudbury will continue the road and water/wastewater improvements on Hyland Drive, between Regent Street to Winchester Avenue,
in Sudbury.

Construction by the City’s Contractor, Garson Pipe Contractors Ltd. will begin May 2023 and is expected to be completed by October 2023.

Work will typically take place during daylight hours Monday to Friday. 

Construction Details:

  • Sidewalk installation on the south side of Hyland Drive from Wellington Heights to west of Killarney Avenue
  • Surface asphalt from Wellington Heights to Winchester Avenue
  • Landscaping and driveway restoration

During construction, there may be dust and noise in the area. The City makes every effort to reduce the impact to nearby residents and business owners. Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.
 

Questions about construction can be directed to:

Project Manager:
Krista Trafford
249-377-9760 
Krista.Trafford@greatersudbury.ca

 

2023 Season Start-Up Notice

Presentation Transcript

Hyland Drive 1

Hyland Drive 2

Wellington Heights

Project Information

Pre-Construction Notice

Construction Notice

COVID-19 Resident Letter

Cold Weather Notice

Construction Notice Update

Project Manager:

Miranda Edwards
705-674-4455, extension 4246
Miranda.Edwards@greatersudbury.ca