Dell Street

The City of Greater Sudbury will be completing road reconstruction on Dell Street from Snowdon Avenue to Notre Dame Avenue.

Construction by the City’s Contractor, Bélanger Construction Ltd. will be carried out between April 2021 and November 2021.

Work will take place Monday to Friday, 7:00 a.m. to 5:00 p.m.

Final asphalt and restoration will be completed by September 2022.

Please note these timelines are subject to change.

Construction Details:
• Road reconstruction
• New sidewalk on both sides of the road
• New watermain and wastewater improvements
• Intersection improvements
• Streetlight improvements

Construction Notice

 

Project Manager:
Brad Johns, P.Eng.
705-674-4455, extension 3625