David Street and John Street

 The City of Greater Sudbury will be completing stormwater improvements on City owned property off John Street, (Sudbury), between David Street and John Street.

Construction Details:
• Construction of a cast in place 25ft x 38ft concrete stormwater treatment structure on the existing storm sewer below ground level off of John Street.
• Site Excavation and removal of 21 metres of existing storm sewer.
• Site access, grading and restoration.

Expected Start Date: Summer 2021
Expected End Date: Fall/Winter 2021

The construction phase of the Project is anticipated to be carried out between July and December.

Pre-Construction Notice

Construction Notice

Public Notice

Construction Notice Update

Project Manager:
Kevin Reynish
705-674-4455, extension 3613