Martindale Road - Complete
ENG20-52 Bridge Rehabilitation, Martindale Road Bridge #1532
The City of Greater Sudbury will be completing road improvements on Martindale Road between MR55 & Copper St.
Construction Details:
- Single Lane Traffic
- Remove and replace the existing asphalt, sidewalk, curb & gutter, guiderail.
- Concrete repairs
- Waterproofing
Construction by the City’s contractor, Belanger Construction Ltd., will be carried out between June, 2020 and October 2020.
Work will take place Monday to Friday,7:00 am to 7:00 pm.
Final asphalt to be completed in the 2020 construction season.
The construction phase of the Project is anticipated to be carried out between June 2020 and October 2020
*Timeline is subject to change*