Frood Road

Asphalt Rehabilitation

The City of Greater Sudbury will be completing road improvements on Frood Road (MR 42) between Elm Street (MR 35) and College Street (MR 63).

Construction by the City’s Contractor, Teranorth Construction & Engineering Limited will be completed in the following phases:

Phase 1 – Will be carried out from October 2020 to November 2020.
Phase 2 – Will be carried out from June 2021 to August 2021.

Construction Details:

Phase 1:
• Placement of base asphalt

Phase 2:
• Placement of surface asphalt
• Spot repair of concrete curb and sidewalk
• Repair of storm structures

During construction, there may be dust and noise in the area. The City makes every effort to reduce the impact to nearby residents and business owners. Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.

Questions about construction can be directed to:

Project Manager:
Miranda Edwards
705-674-4455, extension 4246
miranda.edwards@greatersudbury.ca