2020

2020 Bridge Capital Project Summary

2020 Utilities Meeting

The Annual Utilities Meeting is being held on Wednesday, May 26, 2020. The purpose of this meeting is for the City and the utility companies to coordinate and discuss the requirements for the various utility projects happening during the 2020 construction season .

Agenda

Opening Remarks

CGS 2020 Capital Projects

2020 Tender Schedule

Utility Companies Proposed Projects

Citywide Advanced Metering Infrastructure

Locates and Road Occupancy

Adjournment

Ash Street

Ash Street (Lively) from Maple Street to the South End

The City of Greater Sudbury will be completing road, water and sanitary improvements on Ash Street (Lively), between Maple Street and the southern limit.

Construction by the City’s contractor, Hollaway Equipment Rental Ltd., will be carried out between
May 15 and September 2020. Work will take place Monday to Friday, 7:00am to 7:00pm.

Final asphalt will be completed on September 25, 2020. Please note these timelines are subject to change.

Construction Details:

  • Excavate and install a new watermain on Ash Street with new water services to houses;
  • Complete interior plumbing works to connect the water service to the existing plumbing where required;
  • Abandon in-place, the existing rear yard watermain and services;
  • Realign and replace or abandon sections of the rear yard sanitary sewer main;
  • Storm sewer replacement;
  • Sidewalk replacement and curb and gutter installation along the east side of Ash Street;
  • Repave the road surface;
  • Restore all areas affected by construction

During construction, there may be dust and noise in the area. The City makes every effort
to reduce the impact to nearby residents and business owners. Thank you for your
patience as we work to improve the roads and infrastructure in your neighbourhood. The
City of Greater Sudbury and its contractors are committed to public safety and will monitor
the ongoing progress of construction.

Project Manager:

Kerry Loken
705-674-4455 ext. 4309
kerry.loken@greatersudbury.ca

Auger Avenue

The City of Greater Sudbury will be completing road improvements on Auger Avenue between Falconbridge Road and Hawthorne Drive

Construction Details:

  •  Road Resurfacing
  • Addition of new sidewalk on the west side between Falconbridge Road and Hawthorne Drive
  • Replacement of concrete curb
  • Sidewalk repair (where required)

Expected Start Date: Spring/Summer 2020
Expected End Date: Fall/Winter 2020

*Timeline is subject to change*

Files related to this project include:

Active Transportation

Proposed Scope of Work

Impact of Construction

Impact of Service

Project Manager:    
Andrew Peltomaki
705-674-4455, extension (4392)
andrew.peltomaki@greatersudbury.ca

 

 

Brady Street

Asphalt Rehabilitation

The City of Greater Sudbury will be completing road improvements on Brady Street (MR55) from the CPR Underpass to Keziah Court and on Minto Street from Brady Street (MR55) to Larch Street.

Construction by the City’s contractor, Interpaving Ltd., will be carried out between June 2020 and November 2020

Construction Details:

  • Removal of top lift of asphalt and placement of new asphalt
  • Spot repair of concrete curb and sidewalk
  • Installation of pedestrian crossover at Memorial Park
  • Upgrades to the traffic signals at Brady Street and Minto Street intersection

During construction, there may be dust and noise in the area. The City makes every effort to reduce the impact to nearby residents and business owners. Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.

Coniston Creek Pedestrian Bridge

ENG20-50 Coniston Creek Bridge Replacement

The City of Greater Sudbury will be replacing a pedestrian bridge over Coniston Creek, 100 m east of Poplar Street.

Construction Details:

  • Removal and replacement of the superstructure,
  • Removal and replacement of existing abutments,
  • Installation of new metal tube traffic barrier on bridge,
  • New asphalt pavement on pathway approaches.

Construction by the City’s contractor,  Dominion Construction, will be carried out between June, 2020 and October 2020.

Work will take place Monday to Friday,7:00 am to 7:00 pm. Final asphalt to be completed in the 2020 construction season.

*Timeline is subject to change*

Related Documents

Pre-Construction Notice
Construction Notice
Public Information Session
Resident Notice
Plan
Section

On March 24, 2020, the Province of Ontario classified the construction industry as essential. Work on the approved 2020 capital budget is ongoing and the City is committed to the planned infrastructure improvements.

Under normal circumstances, the City would hold public information sessions to explain these projects and their impact on communities. Instead, we are publishing information online and asking residents to review these documents from their homes.

Project Manager:  
Jody Rybachuk
705-674-4455, extension 4493
Jody.Rybachuk@greatersudbury.ca

Dean Avenue and Jane Street

The City of Greater Sudbury will be completing road and water/wastewater improvements on Dean Street and Jane Street, Sudbury, between Lorne Street and Landsend.

Construction by the City’s contractor,

Garson Pipe Contractors, will be carried out between May 4, 2020 and the fall of 2020. Work will take place Monday to Friday, 7:00am to 7:00pm.

Final asphalt will be completed in the fall of 2020.

Please note these timelines are subject to change. Construction Details:

  • Road reconstruction
  • New sidewalk and asphalt boulevard
  • Watermain replacement
  • Sewer spot repairs

Project Manager:
Marc Khoury
705-674-4455, extension 2935
marc.khoury@greatersudbury.ca

Desmarais Road

Desmarais Road (Valley East)

Asphalt Rehabilitation

The City of Greater Sudbury will be completing road improvements on Desmarais Road (Valley East) between Talon Street to Gravel Drive.

Construction by the City’s contractor, Garson Pipe Contractors Ltd., will be carried out between June 2020 and September 2020.

Construction Details:

  • In-Place Recycling of Existing Asphalt
  • Placement of New Asphalt
  • Drainage Improvements including some ditching and road culvert replacements

During construction, there may be dust and noise in the area. The City makes every effort to reduce the impact to nearby residents and business owners. Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.

Questions about construction can be directed to:

Project Manager:

Miranda Edwards
705-674-4455 ext. 4246
miranda.edwards@greatersudbury.ca

Dominion Drive

Pavement Rehabilitation and Infrastructure improvements on Dominion Drive from Municipal Road 80 to Elmview Drive.

The City of Greater Sudbury would like to thank the area residents for their patience during the ongoing construction over the past year.  This Construction Notice Update is to inform residents that work will resume on April 14, 2020.

By the end of July 2020, the following will occur:

  • Road and multiuse path restoration at the Box Culvert
  • Completion of the multiuse path
  • Shouldering and road widening
  • Driveway and front yard restoration
  • Municipal Road 80 Traffic Signal Improvements
  • Adjustment of structures and completion of roadway Asphal

Should any issues arise or if there is anything you wish to discuss, please contact the Project Manager listed below

We appreciate your patience and cooperation with this important project.  

Questions about construction can be directed to:

Project Manager:   
Kevin Reynish,
705-674-4455, extension 3613
kevin.reynish@greatersudbury.ca

 

Elm and Beatty Streets

Construction by the City’s contractor, Garson Pipe Contractors, will be completed by Fall 2020.

The following work will occur:

  • New Pavement
  • Curb and sidewalk replacement
  • Sewer spot repairs
  • Final Restoration

Please note this timeline is subject to change.

During construction, there may be dust and noise in the area. The City makes every effort to reduce the impact to nearby residents and business owners. Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.

Should any issues arise or if there is anything you wish to discuss, please contact the Project Manager below.
We appreciate your patience and cooperation with this important project.
Questions about construction can be directed to:
 
Project Manager:
Marc Khoury
705-674-4455, extension 2935
marc.khoury@greatersudbury.ca

 

 

Elm Street

The City of Greater Sudbury will be completing road rehabilitation and watermain
improvements on Elm Street, between Pine Street and Elgin Street.


Construction by the City’s contractor,

Denis Gratton Construction Limited,
will be carried out from mid April 2020 and be completed in late summer 2020.

Work will take place Monday to Friday

7:00am to 6:00pm.

Please note these timelines are subject to change.

Construction Details:

  • Watermain Replacement
  • Watermain Lining
  • Sewer Upgrades
  • Road Resurfacing

Project Manager:
Marc Khoury
705-674-4455, extension 2935
marc.khoury@greatersudbury.ca

Fourth Avenue

Fourth Avenue (Sudbury)

Asphalt Rehabilitation

The City of Greater Sudbury will be completing road and water improvements on Fourth Avenue, Sudbury, between Bancroft Drive and Greenwood Drive.

Construction by the City’s contractor,  Teranorth Construction and Engineering Ltd.,  will be carried out between May 11, 2020 and September 2020.

Work will take place Monday to Friday,
7:00am to 6:00pm.

Final asphalt to be completed in the 2020 construction season.

Please note these timelines are subject to change.

Construction Details:

  • Supply and Placement of Hot Mix Asphalt
  • Drainage Improvements including ditching
  • Driveway Restoration
  • Various water service replacements (history of freezing)    

During construction, there may be dust and noise in the area. The City makes every effort to reduce the impact to nearby residents and business owners. Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.

Questions about construction can be directed to:

Project Manager
Andrew Peltomaki
705-674-4455 ext. 4392
andrew.peltomaki@greatersudbury.ca
 

Frood Road

Asphalt Rehabilitation

The City of Greater Sudbury will be completing road improvements on Frood Road (MR 42) between Elm Street (MR 35) and College Street (MR 63).

Construction by the City’s Contractor, Teranorth Construction & Engineering Limited will be completed in the following phases:

Phase 1 – Will be carried out from October 2020 to November 2020.
Phase 2 – Will be carried out from June 2021 to August 2021.

Construction Details:

Phase 1:
• Placement of base asphalt

Phase 2:
• Placement of surface asphalt
• Spot repair of concrete curb and sidewalk
• Repair of storm structures

During construction, there may be dust and noise in the area. The City makes every effort to reduce the impact to nearby residents and business owners. Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.

Questions about construction can be directed to:

Project Manager:
Miranda Edwards
705-674-4455, extension 4246
miranda.edwards@greatersudbury.ca

 

Hawthorne Drive

Hawthorne Drive, Sudbury

Watermain Lining

The City of Greater Sudbury will be completing Watermain Lining on Hawthorne Drive, Sudbury, between Patrick Avenue and Delaware Avenue.

Construction by the City’s contractor, Fer-Pal Construction Limited, will be carried out between
May 2020 and October 2020.

Construction Details:

  • Install temporary above-ground water supply system
  • Watermain lining
  • Restoration to affected areas

During construction, there may be dust and noise in the area. The City makes every effort to reduce the impact to nearby residents and business owners. Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.

Project Manager:
Marc Khoury
705-674-4455, extension 2935
marc.khoury@greatersudbury.ca

Henry Street

Henry Street (Garson)

The City of Greater Sudbury will be completing road and water improvements on Henry Street, Garson, between McDougall Street and Rule Street.

Construction by the City’s contractor, Hollaway Equipment Rental Ltd., will be carried out between June and October 2020.

Work will take place Monday to Friday, 7:00 am to 7:00 pm.

Final asphalt will be completed fall 2020.

Please note timelines are subject to change

Construction Details:

  • Excavate and install a new watermain along Henry Street
  • Installation of new water services to houses along the north side of Henry Street
  • Abandon in place, the existing rear yard watermain and services
  • Complete interior plumbing works to connect the water service to the existing plumbing where required. Those homeowners affected will be contacted separately.
  • Storm sewer replacement
  • Curb and gutter replacement
  • Repave the road surface
  • Restore all areas affected by construction

Letter to Residents

Expected Start Date: Spring/Summer 2020

Expected End Date: Fall/Winter 2020

The construction phase of the Project is anticipated to be carried out between June and October 2020.

During construction, there may be dust and noise in the area. The City makes every effort to reduce the impact to nearby residents and business owners. Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.

Project Manager:

Kerry Loken
705-674-4455 ext. 4309
kerry.loken@greatersudbury.ca
 

Hidden Ridge Court

Hidden Ridge Court (Sudbury)

Surface Asphalt Placement

The City of Greater Sudbury will be completing surface asphalt placement on Hidden Ridge Court, Sudbury, from Moonrock Avenue to the cul-de-sac.

Construction Details:

  • Supply and Placement of Hot Mix Asphalt


Expected Start Date: Spring/Summer 2020

Expected End Date: Fall/Winter 2020

Project Manager
Andrew Peltomaki
705-674-4455 ext. 4392
andrew.peltomaki@greatersudbury.ca
 

High Falls Road

High Falls Road Bridge

The City of Greater Sudbury will be completing road improvements on High Falls Road, 1.2 km north of MR 5 Spanish River Road.
 
Construction Details:

  • Replacing existing bridge with pre-cast concrete girder bridge.
  • Constructing temporary detour bridge to maintain traffic.
  • Installing new guide rails and energy attenuating end treatment.
  • Repaving bridge approaches

Expected Start Date: Summer 2020
Expected End Date: Fall 2020

*Timeline is subject to change*

Related Files:

On March 24, 2020, the Province of Ontario classified the construction industry as essential. Work on the approved 2020 capital budget is ongoing and the City is committed to the planned infrastructure improvements.

Under normal circumstances, the City would hold public information sessions to explain these projects and their impact on communities. Instead, we are publishing information online and asking residents to review these documents from their homes.

    Questions about construction can be directed to:

    Project Manager:    
    Chris Cornell
    705-674-4455, extension 4239
    chris.cornell@greatersudbury.ca

     

     

    Ironside Lake Road

    Bridge Replacement


    The City of Greater Sudbury will be completing road and bridge Improvements on Ironside Lake Road, 0.3kM West of MR 84 Moose Mountain Mine Road.  

    Construction Details:

    • Replace existing bridge with a steel modular bridge.
    • Improve approach road profile and roadside safety features including steel beam guide rails and energy attenuating end treatments.
    • Construct a temporary detour bridge to maintain traffic during construction.

    Expected Start Date: Summer 2020
    Expected End Date: Fall 2020

    Related Documents:

    The construction phase of the Project is
    anticipated to be carried out between July 2020 and October 2020.

    *Timeline is subject to change*
        

    Project Manager:    
    Chris Cornell
    705-674-4455, extension 4239
    chris.cornell@greatersudbury.ca


       

    Kelly Lake Road

    The City of Greater Sudbury will be completing road and wastewater improvements on
    Kelly Lake Road, Sudbury, between Copper Street and Junction Creek Bridge.

    map of Kelly Lake Road constructionConstruction Details:
    • Road reconstruction
    • New sidewalk and cycle facility
    • Sewer and wastewater improvements
    • Intersection improvements

    Expected Start Date: Fall 2020
    Expected End Date: Fall 2021
    *Timeline is subject to change*

    Pre-Construction Notice

    Proposed Scope of Work

    Project Overview and More Information

    Season Startup

    Project manager: 
    Miranda Edwards
    705-674-4455, extension 4246
    Miranda.Edwards@greatersudbury.ca 

    Larocque Avenue

    Larocque Avenue (Val Caron)

    Surface Asphalt Placement

    The City of Greater Sudbury will be completing surface asphalt placement on Larocque Avenue, Val Caron, from Guimond Avenue to cul-de-sac.

    Construction Details:

    • Supply and Placement of Hot Mix Asphalt
    • Complete concrete sidewalk from 30m north of Guimond Avenue to 130m north of Guimond Avenue (west side)


    Expected Start Date: Spring/Summer 2020

    Expected End Date: Fall/Winter 2020

    Project Manager
    Andrew Peltomaki
    705-674-4455 ext. 4392
    andrew.peltomaki@greatersudbury.ca

    Martindale Road

    ENG20-52 Bridge Rehabilitation, Martindale Road Bridge #1532

    The City of Greater Sudbury will be completing road improvements on Martindale Road between MR55 & Copper St.

    Construction Details:

    • Single Lane Traffic
    • Remove and replace the existing asphalt, sidewalk, curb & gutter, guiderail.
    • Concrete repairs
    • Waterproofing

    Construction by the City’s contractor, Belanger Construction Ltd., will be carried out between June, 2020 and October 2020.

    Work will take place Monday to Friday,7:00 am to 7:00 pm.

    Final asphalt to be completed in the 2020 construction season.

    The construction phase of the Project is anticipated to be carried out between June 2020 and October 2020

    *Timeline is subject to change*

    Related Documents:

    Pre-Construction Notice
    Construction Notice
    Resident Notice
    Public Information Session
    Plan
    Section

    Project Manager:
    Jody Rybachuk
    705-674-4455, extension 4493
    Jody.Rybachuk@greatersudbury.ca

    Maxam Landing

    oxam Landing (Sudbury)

    Asphalt Rehabilitation

    The City of Greater Sudbury will be completing road improvements on Moxam Landing Road, Sudbury, from Gibson Road to 800 m South.

    Construction by the City’s contractor,  Teranorth Construction and Engineering Ltd.,  will be carried out between May 11, 2020 and September 2020.

    Work will take place Monday to Friday, 7:00am to 6:00pm.

    Final asphalt to be completed in the 2020 construction season.
    Please note these timelines are subject to change.
    Construction Details:

    • Full Depth Removal of Existing Asphalt
    • Supply and Placement of Hot Mix Asphalt
    • Drainage Improvements including ditching
    • Rock Removal to accommodate ditching
    • Guide Rail Replacements
    • Driveway Restoration    

    During construction, there may be dust and noise in the area. The City makes every effort to reduce the impact to nearby residents and business owners. Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.

    Project Manager
    Andrew Peltomaki
    705-674-4455 ext. 4392
    andrew.peltomaki@greatersudbury.ca
     

    Montrose Watermain Booster Station Upgrades

    The City of Greater Sudbury will be upgrading the Montrose Booster Station at the corner of Montrose Avenue and Thorncliffe Court.



    Construction by the City’s contractor,

    Cast Construction Inc., will be carried out between July 2020 and Spring 2021.

    Work will take place Monday to Friday, 7am to 7pm.

    Final asphalt will be completed 2021.

    Please note these timelines are subject to change.

    Construction Details:

    • Installation of a below ground water booster chamber with pumps
    • Installation of an above ground electrical and control panel
    • Temporary water by-pass around construction area
    • Restoration as required of adjacent properties and road

    Project Manager:

    Kerry Loken
    705-674-4455 extension 4309
    kerry.loken@greatersudbury.ca


    Covid-19 Letter to Residents

    Moose Mountain Mine Road

    Bridge Reconstruction

    The City of Greater Sudbury will be completing road and bridge improvements on Moose Mountain Mine Road (MR 84), Capreol area, 1.0km South of Milnet Road."

    Construction Details:

    • Bailey Bridge Replacement
    • Asphalt Paving
    • Guiderail Installation
    • Temporary Detour Bailey Bridge

    Expected Start Date: mid June 2020
    Expected End Date: mid October 2020

    Related Documents

    Pre-Construction Notice
    Resident Notice
    Public Information Session
    Plan
    Section

    The construction phase of the Project is anticipated to be carried out between June 15, 2020 and October 16, 2020.

    *Timeline is subject to change due to COVID-19 Restrictions*

    Project Manager:    
    Chris Cornell
    705-674-4455, extension 4239
    chris.cornell@greatersudbury.ca

    MR 35 - Road Widening and Infrastructure Improvements

    The City of Greater Sudbury is widening Municipal Road 35 (MR35) from Notre Dame Street East, Azilda to Highway 144, Chelmsford. The new roadway will include road widening to four lanes from Notre Dame East to Notre Dame West and to five lanes from Notre Dame West to Highway 144 (including a continued shared centre turn lane). In addition, the new roadway will include intersection improvements, traffic signal upgrades, paved shoulders with rumble strips, drainage improvements, new signage, pavement markings and guide rails, where required. Approximately 975 metres of water main upgrades will also be undertaken near the Chelmsford section of this corridor.

    Project Background

    MR35 is an important gateway to the community of Greater Sudbury. MR35 is an arterial road that connects the communities of Azilda, Chelmsford, Dowling, Levack, and Onaping to the downtown. The widening of MR35 to install additional driving lanes was recommended in the Sudbury Regional Transportation Study (March 1992), and reaffirmed in the 2005 Transportation Master Plan Study and the 2015 Transportation Master Plan Study for the City of Greater Sudbury.

    Project Construction

    Construction of MR35 began in the fall of 2018 with a culvert replacement contract.

    In 2019, MR35 was widened from two (2) to four (4) lanes from Notre Dame Street East (Azilda) to Notre Dame Street West (Azilda). Intersection and drainage improvements were also completed along this section of MR35. Final layer of asphalt and restoration work to be completed in the Spring of 2020.

    In 2020, construction is planned for the widening and infrastructure improvements along MR35 from Notre Dame Street West (Azilda) to Highway 144 (Chelmsford).

    FAQ

    MR35 Photos

    2018 Culvert Replacement Contract 

    Key Plan

    MR35 Contract 1 - Notre Dame Street East (Azilda) to Notre Dame Street West (Azilda)

    MR35 Information Boards - Sept 27, 2018 

    MR35 Key Plan 

    MR35 Contract 2 - Highway 144 (Chelmsford) to Notre Dame Street West (Azilda)

    Road and watermain improvements on Municipal Road 35 (MR35), between Highway 144 (Chelmsford) and 300 m east of Notre Dame West (Azilda) will be carried out between Summer 2020 and Fall 2021. Work will take place Monday to Friday, 7:00 AM to 7:00 PM.

    Final asphalt will be completed in the Fall of 2021. Please note these timelines are subject to change.

    Construction Notice

    Project Overview and Next Steps

    Mumford Road

    Mumford Road (Sudbury)

    Asphalt Rehabilitation

    The City of Greater Sudbury will be completing road improvements on Mumford Road, Sudbury, between Vagnini Court and Duhamel Road.

    Construction by the City’s contractor,  Teranorth Construction and Engineering Ltd.,  will be carried out between May 11, 2020 and September 2020. Work will take place Monday to Friday, 7:00am to 6:00pm.

    Final asphalt to be completed in the 2020 construction season.

    Please note these timelines are subject to change.

    Construction Details:

    • Full Depth Removal of Existing Asphalt
    • Supply and Placement of Hot Mix Asphalt
    • Drainage Improvements including ditching
    • Driveway Restoration    

    During construction, there may be dust and noise in the area. The City makes every effort to reduce the impact to nearby residents and business owners. Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.

    Project Manager
    Andrew Peltomaki
    705-674-4455 ext. 4392
    andrew.peltomaki@greatersudbury.ca

    Nicolet Street

    Nicolet Street, Sudbury

    Watermain Lining

    The City of Greater Sudbury will be completing Watermain Lining on Nicolet Street, Sudbury, between Secord Court and Nicolet Street (Cul-de-sac).

    Construction by the City’s contractor, Fer-Pal Construction Limited, will be
    carried out between May 2020 and October 2020.

    Construction Details:

    • Install temporary above-ground water supply system
    • Watermain lining
    • Restoration to affected areas

    During construction, there may be dust and noise in the area. The City makes every effort
    to reduce the impact to nearby residents and business owners. Thank you for your
    patience as we work to improve the roads and infrastructure in your neighbourhood. The
    City of Greater Sudbury and its contractors are committed to public safety and will monitor
    the ongoing progress of construction.

    Project Manager:
    Marc Khoury
    705-674-4455, extension 2935
    marc.khoury@greatersudbury.ca

    Notre Dame Avenue (Valley East)

    Asphalt Rehabilitation

    The City of Greater Sudbury will be completing road improvements on Notre Dame Avenue (Valley East) between Dominion Drive and 760 m North of Dominion Drive.

    Construction by the City’s contractor, Interpaving Ltd., will be carried out between June 2020 and September 2020.

    Construction Details:

    • In-Place Recycling of Existing Asphalt
    • Placement of New Asphalt
    • Drainage Improvements including some ditching and road culvert replacements

    Your street is part of the City of Greater Sudbury’s Council approved asphalt resurfacing program. Work will be completed in the 2020 construction season. The expected start date will be communicated in a follow-up notice closer to construction.

    Project Manager:
    Miranda Edwards
    705-674-4455 ext. 4246
    miranda.edwards@greatersudbury.ca

    Old Hwy 17 (MR55)

    Asphalt Rehabilitation

    Old Hwy 17 (MR55) from 195 East of Koti Road to Horizon Drive.

    The City of Greater Sudbury will be completing road improvements on Old Hwy 17 (MR55) from 195 East of Koti Road to Horizon Drive.

    Construction by the City’s contractor, Garson Pipe Contractors Ltd.,will be carried out from May 2020 to July 2020.

    Construction Details:

    • In-place recycling of existing asphalt
    • Placement of new asphalt
    • Replacement of road culverts


    The City makes every effort to reduce the impact to nearby residents and business owners. Plans are in place to manage traffic in the area to ensure the safety of workers and the travelling public. You may experience some delays .At times, the roadway may be reduced to one lane of traffic to accommodate construction.

    Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.

     

    Old Hwy 69 (MR80)

    Asphalt Rehabilitation

    Old Hwy 69 (MR80) from Maley Dr Exit Ramp to Donaldson Dr.

    The City of Greater Sudbury will be completing road improvements on Old Hwy 69 (MR80) from Maley Dr Exit Ramp to Donaldson Dr.

    Construction by the City’s contractor, Garson Pipe Contractors Ltd.,
    will be carried out from July 2020 to September 2020.

    Construction Details:

    • Replacement of road crossing culverts

    This is a Designated Construction Zone. The speed limit within this area will be reduced from 80km/hr to 60km/hr through construction.

    The City makes every effort to reduce the impact to nearby residents and business owners. Plans are in place to manage traffic in the area to ensure the safety of workers and the travelling public. You may experience some delays .At times, the roadway may be reduced to one lane of traffic to accommodate construction.
    Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.

    Project Manager:

    Miranda Edwards
    705-674-4455 ext. 4246
    miranda.edwards@greatersudbury.ca

    Palladium Place

    Palladium Place (Sudbury)

    Surface Asphalt Placement

    The City of Greater Sudbury will be completing surface asphalt placement on Palladium Place, Sudbury, from  Topaz Court to Corsi Hill.

    Construction Details:

    • Supply and Placement of Hot Mix Asphalt

    Expected Start Date: Spring/Summer 2020

    Expected End Date: Fall/Winter 2020

    Project Manager
    Andrew Peltomaki
    705-674-4455 ext. 4392
    andrew.peltomaki@greatersudbury.ca

    Paris Notre Dame Bikeway

    The City of Greater Sudbury will be completing active transportation improvements on Notre Dame Avenue between Wilma Street and Lasalle Boulevard. Construction by the City’s Contractor, Interpaving Ltd., will be carried out between June and October 2020.

    Work will take place Monday to Friday, 7:00 am to 7:00 pm. Please note these timelines are subject to change.

    Construction Details:
    • New cycle facility on east and west sides of
    Notre Dame Avenue
    • New sections of curb and sidewalk
    • Landscaping
    • Street lighting and intersection improvements

    During construction, there may be dust and noise in the area. The City makes every effort to reduce the impact to nearby residents and business owners. Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.

    Construction Notice

    Letter to Residents

    Ramsey Lake Road

    Asphalt Rehabilitation

    The City of Greater Sudbury will be completing road improvements on Ramsey Lake Road (MR39) between Paris Street (MR80) and South Bay Road.

    Construction by the City’s Contractor, Teranorth Construction & Engineering Limited will be completed in the following phases:

    Phase 1 – Will be carried out from October 2020 to November 2020.
    Phase 2 – Will be carried out from June 2021 to September 2021.

    Construction Details:

    Phase 1:
    • Replacement of road culverts

    Phase 2:
    • Placement of new asphalt
    • Spot repair of concrete curb and sidewalk
    • Installation of signalized pedestrian crosswalk at Science North
    • Replacement of Road Culvert at University Road
    • Installation of Steel Beam Guide Rail

    During construction, there may be dust and noise in the area. The City makes every effort to reduce the impact to nearby residents and business owners. Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.

    Questions about construction can be directed to:

    Project Manager:
    Miranda Edwards
    705-674-4455, extension 4246
    miranda.edwards@greatersudbury.ca

    Richelieu Court

    Richelieu Court & Landreville Drive (Sudbury)

    Surface Asphalt Placement

    The City of Greater Sudbury will be completing surface asphalt placement on Richelieu Court (Sudbury) from Maley Drive to the cul-de-sac as well as Landreville Drive from Richelieu Court to the cul-de-sac (see map).

    Construction Details:

    • Supply and Placement of Hot Mix Asphalt

    Expected Start Date: Spring/Summer 2020

    Expected End Date: Fall/Winter 2020

    Project Manager
    Andrew Peltomaki
    705-674-4455 ext. 4392
    andrew.peltomaki@greatersudbury.ca

    Rideau Street

    Rideau Street, Sudbury

    Watermain Lining

    The City of Greater Sudbury will be completing Watermain Lining on Rideau Street, Sudbury, between Lasalle Boulevard and Lavoie Street.

    Construction by the City’s contractor, Fer-Pal Construction Limited, will be carried out between May 2020 and October 2020.

    Construction Details:

    • Install temporary above-ground water supply system
    • Watermain lining
    • Restoration to affected areas

    During construction, there may be dust and noise in the area. The City makes every effort to reduce the impact to nearby residents and business owners. Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.

    Project Manager:
    Marc Khoury
    705-674-4455, extension 2935
    marc.khoury@greatersudbury.ca

    Rita Street

    Rita Street, (Sudbury)

    Watermain Replacement

    The City of Greater Sudbury will be completing road road and water/wastewater improvements on Rita Street (Sudbury) between Wilfred Street to the End.

    Construction by the City’s contractor, Teranorth Construction, will be carried out between May 2020 and October 2021. Work will take place Monday to Friday, 7 am and 7 pm.

    Final asphalt will be completed in the fall of 2021.

    Please note these timelines are subject to change.

    Construction Details:

    • Replace watermain including water services to property line
    • Replace sanitary sewer services to property line
    • Full Depth Removal of Existing Asphalt
    • Supply and Placement of Hot Mix Asphalt
    • Drainage Improvements including ditching
    • Construction of new cul-de-sac

    During construction, there may be dust and noise in the area. The City makes every effort to reduce the impact to nearby residents and business owners. Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction

    Project Manager
    Andrew Peltomaki
    705-674-4455 ext. 4392
    andrew.peltomaki@greatersudbury.ca
     

    Scarlett Road

    Scarlett Road, Sudbury

    Watermain Lining

    The City of Greater Sudbury will be completing Watermain Lining on Scarlett Road, Sudbury, between Second Avenue and Greenbriar Drive.

    Construction by the City’s contractor, Fer-Pal Construction Limited, will be carried out between May 2020 and October 2020.

    Construction Details:

    • Install temporary above-ground water supply system
    • Watermain lining
    • Restoration to affected areas

    During construction, there may be dust and noise in the area. The City makes every effort to reduce the impact to nearby residents and business owners. Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.

    Project Manager:
    Marc Khoury
    705-674-4455, extension 2935
    marc.khoury@greatersudbury.ca

    Scenic Drive

    Scenic Drive (Valley East) Asphalt Rehabilitation

    The City of Greater Sudbury will be completing road improvements on Scenic Drive (Valley East) between Valleyview Road and South End of Scenic Drive.

    Construction by the City’s contractor, Interpaving Ltd., will be carried out between May 2020 and September 2020.

    Construction Details:

    • In-Place Recycling of Existing Asphalt
    • Placement of New Asphalt
    • Drainage Improvements including some ditching and road culvert replacements

    During construction, there may be dust and noise in the area. The City makes every effort to reduce the impact to nearby residents and business owners. Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.

    Project Manager:
    Miranda Edwards
    705-674-4455 ext. 4246
    miranda.edwards@greatersudbury.ca

    Skead Road

    Asphalt Rehabilitation

    Skead Road (MR86) from Radar Road (MR85) to Airport Terminal Road.

    The City of Greater Sudbury will be completing road improvements on Skead Road (MR86) from Radar Road (MR85) to Airport Terminal Road.

    Construction by the City’s contractor, Garson Pipe Contractors Ltd., will be carried out from early May 2020 to July 2020.

    Construction Details:

    • In-place recycling of existing asphalt
    • Placement of new asphalt
    • Replacement of road culverts


    The City makes every effort to reduce the impact to nearby residents and business owners. Plans are in place to manage traffic in the area to ensure the safety of workers and the travelling public. You may experience some delays .At times, the roadway may be reduced to one lane of traffic to accommodate construction.

    Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.

     

    Spanish River Road Bridge

    The City of Greater Sudbury will be completing road and bridge improvements on Spanish River Road, Beaver Lake area, 3.1km West of Manninen Road.



    Construction Details:

    • Bailey Bridge Replacement
    • Asphalt Paving
    • Guiderail Installation
    • Full Road Closure at Bridge Location (Detour via Manninen Road and Hwy. 17)

    Expected Start Date: Mid June 2020

    Expected End Date: Early October 2020

    The construction phase of the Project is anticipated to be carried out between June 15, 2020 and October 2, 2020.

    Related Documents

    Pre-Construction Notice
    Public Information Session
    Resident Notice
    Plan
    Section
    Detour Plan

    *Timeline is subject to change due to COVID-19 Restrictions*

    Project Manager:    
    Chris Cornell
    705-674-4455, extension 4239
    chris.cornell@greatersudbury.ca

     

    Sunnyside Road

    Sunnyside Road (Sudbury)

    Asphalt Rehabilitation

    The City of Greater Sudbury will be completing road improvements on Sunnyside Road, Sudbury, between Long Lake Road and Luoma Road.

    Construction by the City’s contractor,  Teranorth Construction and Engineering Ltd.,  will be carried out between April 2020 and September 2020. Work will take place Monday to Friday, 7:00am to 6:00pm.

    Final asphalt to be completed in the 2020 construction season.

    Please note these timelines are subject to change.

    Construction Details:

    • Full Depth Removal of Existing Asphalt
    • Supply and Placement of Hot Mix Asphalt
    • Drainage Improvements including ditching
    • Driveway Restoration    

    During construction, there may be dust and noise in the area. The City makes every effort to reduce the impact to nearby residents and business owners. Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.

    Project Manager
    Andrew Peltomaki
    705-674-4455 ext. 4392
    andrew.peltomaki@greatersudbury.ca

    Surface Treatment - Various Locations

    Surface Treatment, Various Locations

    The City of Greater Sudbury will be completing road improvements in several areas

    Construction by the City’s contractor, Denis Gratton Construction Ltd., will be carried out between June and November, Monday to Friday, 7:00 a.m. to 7:00 p.m.

    Please note these timelines are subject to change.

    Construction Details:

    • In-place full depth reclamation of the road surface (pulverizing)
    • Placement of Granular ‘A’
    • Maintenance of each road until surface treated
    • Emulsified asphalt surface treatment
    • Culvert replacements / ditching, as required

    During construction, there may be dust and noise in the area. The City makes every effort to reduce the impact to nearby residents and business owners. Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.

    Questions about construction can be directed

    Project Manager:
    Rebecca Gilchrist
    705-674-4455 ext. 4218
    rebecca.gilchrist@greatersudbury.ca

    Location maps

    1. Goodwill Drive (Garson)

    2. Goodwill Drive (Garson)

    3. O’Neil Drive West (Garson)

    4. O’Neil Drive West (Garson)

    5. West Bay Road (Skead)

    6. Spanish River Road (Worthington)

    7. Spanish River Road (Worthington)

    8. Spanish River Road (Worthington)

    9. North Shore Black Lake (Lively)

    10. Fairbank Lake Road – MR4 (Worthington)

    11. Fairbank East Road (Whitefish)

    12. Moxam Landing Road (Lively)

    13. Grassy Lake Road (Skead)

    14. Den Lou Road (Whitefish)

    15. McKenzie Road (Chelmsford)

    16. Bruno Street (Azilda)

    17. Montee Rouleau (Chelmsford)

    18. Vermilion Lake Road (Chelmsford)

    19. Theriault Road (Hanmer)

    20. Martin Road (Val Caron)

    21. Bodson Drive West (Val Caron)

    22. Frenchman Lake Road (Hanmer)

    23. Tilton Lake Road (Sudbury)

    24. South Lane (Sudbury)

    25. Pine Hill Road (Sudbury)

    26. Goodwill Drive (Garson)

    27. Goodwill Drive (Garson)

    28. West Bay Road (Skead)

    29. West Bay Road (Skead)

    30. West Bay Road (Skead)

    31. Hill Street (Wahnapitae)

    32. MR4 (Whitefish)

    33. Morgan Road (Chelmsford)

    34. Morgan Road (Chelmsford)

    35. Montpellier Road (Chelmsford)

    36. Edgewater Road (Sudbury)

    37. Bodson Drive West (Val Caron)
     

    Tenth Avenue

    Tenth Avenue (Lively)

    Watermain Improvements

    The City of Greater Sudbury will be completing watermain improvements on Tenth Avenue, Lively, between ‘B’ Street and ‘C’ Street.

    Construction by the City’s Contractor, Teranorth Construction & Engineering Limited, will be carried out in the 2020 Construction season, starting in May.

    Work will take place Monday to Friday, 7am to 6pm.

    Complete road and sidewalk restoration will occur in the future.

    Please note these timelines are subject to change.

    Construction Details:

    • Excavate and install a new Watermain along Tenth Avenue.
    • Installation of new water services to houses along the east side of Tenth Avenue.
    • Abandon in place, the existing rear yard watermain and services.
    • Complete interior plumbing works to connect the water service to the existing pumping where required. Those homeowners affected will be contacted separately.

    During construction, there may be dust and noise in the area. The City makes every effort to reduce the impact to nearby residents and business owners. Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.

    Questions about construction can be directed to:
     

    Project Manager:

    Rebecca Gilchrist
    705-674-4455 ext 4218
    rebecca.gilchrist@greatersudbury.ca

    Valleyview Road

    Asphalt Rehabilitation

    The City of Greater Sudbury will be completing road improvements on Valleyview Road (Valley East) between St. Laurent Street and Martin Road.

    Construction by the City's contractor, Interpaving Ltd., will be carried out between June 2020 and September 2020.

    Construction Details:

    • In-Place Recycling of Existing Asphalt
    • Placement of New Asphalt
    • Drainage Improvements including some ditching and road culvert replacements

    Your street is part of the City of Greater Sudbury’s Council approved asphalt resurfacing program. Work will be completed in the 2020 construction season. The expected start date will be communicated in a follow-up notice closer to construction.
     

    Project Manager:
    Miranda Edwards
    705-674-4455 ext. 4246
    miranda.edwards@greatersudbury.ca

    Wastewater Improvements - Various Locations

    The City of Greater Sudbury will be completing wastewater improvements throughout the City of Greater Sudbury

    Construction by the City’s contractor, Insituform, will be carried out between Summer 2020 and Fall 2020.
    Work will take place Monday to Friday, 7:00am to 7:00pm.

    Please note these timelines are subject to change.

    Construction Details:

    • Structural Lining using Cured-in-Place Pipe (CIPP) of existing sanitary sewer

    Project Manager:
    Marc Khoury
    705-674-4455, extension 2935
    marc.khoury@greatersudbury.ca

     

    Locations include:

    1.Front Street, Capreol, between Young Street and Bloor Street
    2.Godfrey Drive, Copper Cliff, between Serpentine Street and Park Street
    3.Hanna Avenue, Capreol, between Dennie Street and Kelly Street
    4.Harvey Street, Sudbury, between Leslie Street and Mountain Street
    5.Helene Street, Val Caron, between Leo Avenue and Marie Avenue
    6.Highland Crescent, Capreol, North of Oakwood Avenue
    7.Jupiter Court, Sudbury, south of Telstar Avenue
    8.Lincoln Crescent, Capreol, between Dennie Street and Hillcrest Avenue
    9.Lincoln Street, Capreol, between Norman Avenue and Sellwood Avenue
    10.Mabel Avenue, Sudbury, between Kathleen Street and Suffolk Lane
    11.Martindale Road, Sudbury, between Boyce Street and Marcel Street
    12.McKim Street, Sudbury, between Erie Street and Beatty Street
    13.Neelon Avenue, Sudbury, between Weller Street and the dead end
    14.Nickel Street, Copper Cliff, between Balsam Street and Peter Street
    15.Norman Crescent, Val Caron, between Velma Street and Harold Crescent
    16.Notre Dame Avenue, Hanmer, between St Isadore Street and Oscar Street
    17.Odile Street, Hanmer, between Carina Drive and Chenier Street
    18.Peter Street, Copper Cliff, between Church Street and Balsam Street
    19.Railway Avenue, Capreol, between Mooney Street and Dennie Street
    20.Rose Court, Val Caron, north of Dominion Drive
    21.St Raphael Street, Sudbury, between Lourdes Street and the dead end
    22.Swanson Court, Val Caron, between Velma Street and Harry Street
    23.Tenth Avenue, Lively, between C Street and Ninth Avenue
    24.Third Avenue, Coniston, between Cedar Street and Government Road
    25.Third Avenue, Levack, between Cartier Street and 40 m south
    26.Walnut Street, Sudbury, between Regent Street and Lorne Street
    27.Whittaker Street, Sudbury, between Albert Street and Elm Street
    28.Albinson Street, Sudbury, between Arnley Street and Douglas Street
    29.Alder Street, Sudbury, between Walnut Street and Oak Street
    30.Anthony Street, Sudbury, between Regent Street and the end of Anthony Street
    31.Arnley Street, Sudbury, between Horobin Street and the dead end of Arnley Street
    32.Austin Street, Sudbury, between Regent Street and the end of Austin Street
    33.Birch Lane, Garson, between Spruce Street and Birch Street
    34.Birch Street, Garson, between Beech Street and Church Street
    35.Birch Street, Sudbury, between Lorne Street and Oak Street
    36.Bloor Street, Sudbury, between Frood Road and College Street
    37.Carol Street, Val Caron, between Claire Street and Mark Street
    38.Christakos Street, Sudbury, between Howey Drive and the end of Christakos Street
    39.Collins Drive, Copper Cliff, between Power Street and Orford Street
    40.Dennie Street, Capreol, between Pine Street and Hillcrest Avenue
    41.Edna Street, Sudbury, between Haig Street and Buchanan Street
    42.Elm/Spruce Street Easement, Sudbury, between Elm Street and Spruce Street
    43.Ferguson Avenue, Capreol, between Dennie Street and Chapman Street
    44.Fifth Street, Val Caron, between MR80 and Northwood Drive

     

    Westmount Avenue

    Westmount Avenue, Sudbury

    Watermain Lining

    The City of Greater Sudbury will be completing Watermain Lining on Westmount Avenue, Sudbury, between Attlee Avenue and Barrydowne Road.

    Construction by the City’s contractor, Fer-Pal Construction Limited, will be carried out between May 2020 and October 2020.

    Construction Details:

    • Install temporary above-ground water supply system
    • Watermain lining
    • Restoration to affected areas

    During construction, there may be dust and noise in the area. The City makes every effort to reduce the impact to nearby residents and business owners. Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.

    Project Manager:
    Marc Khoury
    705-674-4455, extension 2935
    marc.khoury@greatersudbury.ca