Paris Street

Paris Street, Sudbury - Bridge Rehabilitation 

The City of Greater Sudbury will be completing road and bridge improvements on Paris Street between John Street and Van Horne Street.

Construction by the City’s contractor, Belanger Construction Ltd., will be carried out between July 2022 and November 2022. 

Work will take place Monday to Friday.  

The work in 2022 will be primarily on the underside of the bridge, with deck surface and approach work planned for 2023.

Final asphalt planned to be completed in October, 2023.

Please note these timelines are subject to change.

Construction Details: 

  • Installation of new bike lane on the bridge and approaches.
  • Concrete removals and repair.
  • Deck repairs, waterproofing and paving.
  • Cleaning and coating girder ends.

Construction Notice 

Project Manager: 
Chris Cornell               
705-674-4455, extension 4239         