Ironside Lake Road - Complete

Bridge Replacement


The City of Greater Sudbury will be completing road and bridge Improvements on Ironside Lake Road, 0.3kM West of MR 84 Moose Mountain Mine Road.  

Construction Details:

  • Replace existing bridge with a steel modular bridge.
  • Improve approach road profile and roadside safety features including steel beam guide rails and energy attenuating end treatments.
  • Construct a temporary detour bridge to maintain traffic during construction.

Expected Start Date: Summer 2020
Expected End Date: Fall 2020

Related Documents:

The construction phase of the Project is
anticipated to be carried out between July 2020 and October 2020.

*Timeline is subject to change*
    

Project Manager:    
Chris Cornell
705-674-4455, extension 4239
chris.cornell@greatersudbury.ca