Coniston Creek Pedestrian Bridge - Complete

ENG20-50 Coniston Creek Bridge Replacement

The City of Greater Sudbury will be replacing a pedestrian bridge over Coniston Creek, 100 m east of Poplar Street.

Construction Details:

  • Removal and replacement of the superstructure,
  • Removal and replacement of existing abutments,
  • Installation of new metal tube traffic barrier on bridge,
  • New asphalt pavement on pathway approaches.

Construction by the City’s contractor,  Dominion Construction, will be carried out between June, 2020 and October 2020.

Work will take place Monday to Friday,7:00 am to 7:00 pm. Final asphalt to be completed in the 2020 construction season.

*Timeline is subject to change*

Related Documents

Pre-Construction Notice
Construction Notice
Public Information Session
Resident Notice
Plan
Section

On March 24, 2020, the Province of Ontario classified the construction industry as essential. Work on the approved 2020 capital budget is ongoing and the City is committed to the planned infrastructure improvements.

Under normal circumstances, the City would hold public information sessions to explain these projects and their impact on communities. Instead, we are publishing information online and asking residents to review these documents from their homes.

Project Manager:  
Jody Rybachuk
705-674-4455, extension 4493